Alberta Solar 2
January 31, 2025
Alberta, Canada

Alberta Solar 2

Total Capacity

153 MWdc solar + 60 MW (4hr) battery storage

Location

Alberta, Canada

Mounting Structure

single-axis tracking

Total 1st year
production

252,450 MWh

Total 40 year
production

9,310,356 MWh

ESTIMATED
PRODUCTION YIELD

1,650 kWh/kWdc

avoided
CO2 Emissions

6,598,086 tCO2e

TRANSMISSION
REGULATORY BODY

AESO

Project Description

  • The project has a projected capacity of 153 MWdc solar + 60 MW (4hr) battery storage
  • Located in Southeastern Alberta, adjacent to Proteus Alberta Solar 1 and 3
  • The project has a lease option for 1,027 acres of lands with a local public institution
  • The 153 MWdc generation facility will connect to the transmission grid with a 138kV interconnection
  • Project development schedule estimated to be 20 months and will begin construction Q3 2024. The projected COD date is Q1 2025