Oyster Creek Solar 2
Total Capacity
133 MWdc solar + 50 MW (4hr) battery storage
Location
Texas, USA
Mounting Structure
single-axis tracking
Total 1st year
production
256,025 MWh
Total 40 year
production
9,542,051 MWh
ESTIMATED
PRODUCTION YIELD
1,925 kWh/kWdc
avoided
CO2 Emissions
6,762,284 tCO2e
TRANSMISSION
REGULATORY BODY
ERCOT
Project Description
The project has a projected capacity of 133 MWdc solar + 50 MW (4hr) battery storage
Located adjacent to Oyster Creek Solar 1
The project has a land option on 900 acres of lands with the same owner as Oyster Creek Solar 1
The 133 MWdc will connect to the switching substation of Oyster Creek 1 with a 3.2 mi transmission line
Project development schedule estimated to be 18 months and will begin construction in Q3 2025. The projected COD date is Q2 2026
Project interconnection application filed in July