Red Hawk Solar 1
May 31, 2026
Arizona, USA

Red Hawk Solar 1

Total Capacity

72 MWdc solar

Location

Arizona, USA

Mounting Structure

single-axis tracking

Total 1st year
production

164,448 MWh

Total 40 year
production

6,064,842 MWh

ESTIMATED
PRODUCTION YIELD

2,284 kWh/kWdc

avoided
CO2 Emissions

4,298,047 tCO2e

TRANSMISSION
REGULATORY BODY

WECC

Project Description

  • The project has a projected capacity of 72 MWdc solar
  • The project has a land option on 300 acres of lands with private mining entity
  • The 72 MWdc generation facility would require 1 mi of distribution lines and will connect to the transmission network at 115kV
  • Project development schedule estimated to be 24 months and will begin construction Q3 2025. The projected COD date is Q2 2026